WATER
TREATMENT PLANT
For water
treatment plant, the design will be based on final throughput due to it was not
easy to handle double water treatment plant.
1. Water consumption per tonne FFB
process = 1.5m³ to FFB
2.
Average processing hour =
20 hours
3.
Reservoir capacity =
40 days
Water
requirement for 80 tonne / hour FFB process
= 80 tonne/hr x 1.5
= 120 tonne
water/hour.
5.2
Reservoir Capacity.
Reservoir
capacity = 40 days x 120 tonne
water/hour x 20 hours
= 96000 m³
The
reservoir capacity for 40 days is important during dry season and during high
type (high in chloride).
5.3
Pump Sizing.
For pump
from river to reservoir, the capacity should be higher in case of emergency, it
can pumping at high rate.
Therefore,
propose for = 120m³/hour x Safety factor
=
180m³/hr
Only one
unit required for this station due to have holding capacity of 40 days.
For pump
from reservoir to water clarifier,
= Safety
factor x water requirement
= 1.1 x 120
m³/hr
= 132
m³/hour.
This station need 2 unit of pump where 1 unit running
and the other one on standby.
5.3
Water Clarifier Sizing
Retention
time = 3 hours.
Therefore,
Clarifier capacity = Retention time x
Water requirement/hour
=
3 hours x 120 m³/hr
=
360 m³
5.4
Water Tank Sizing
Allowed
holding time of 4 hours = 4 hours x
water requirement/hr
=
4 x 120m³
=
480 m³
The
water tank is a over head tank where, for all the process will come in gravity
flow.
Waste Water Treatment Plant
Data given:
Steriliser
Condensate = 12% to FFB
Sludge = 50% to FFB
Claybath
water = 0.05% to FFB
At 80 tonne/hour milling capacity, total
amount of waste water produced will be:
Sterilizer condensate = 80tonne/hour x 0.12 = 9.6
tonne/hour
Sludge =
80tonne/hour x 0.50 = 40 tonne/hour
Claybath water = 80tonne/hour x 0.05 %
= 0.04tonne/hour
Total =
49.64 tonne/hour
Based on 20 hours operation per day, 49.64
tonne/hour x 20 hour = 992.8 tonne
For this mill, the layout of effluent
treatment plant is as attached.
0 komentar:
Posting Komentar